Beitbridge-Chirundu highway's new design to cost US$520 000

Beitbridge-Chirundu highway's new design to cost US$520 000
Published: 15 March 2019 (134 Views)
THE Beitbridge-Harare-Chirundu highway dualisation project has been pushed back by a further three months over new designs. This comes as government scouts for a new road designer after Austrian firm Geiger, which initially crafted a detailed design, lost the US$1,2 billion tender last year, the Zimbabwe Independent can report.

In a meeting held between government and local contractors who have since been roped in to replace Chinese firm Anhui Foreign Economic Construction Group Limited Afecc, the two parties agreed that construction work along the highway would only begin after a new road design is crafted.

Before the government cancelled Geiger's contract last year, the Austrian firm had already completed its road designs.
New road designs are expected to take three months upon which construction will commence, Zimbabwe Building Contractors' Association (ZBCA) vice-president Gerald Chipumha says.

"We had a meeting last week. Government wants to kick-start the project soon but since Geiger lost the tender, there has to be a new design. So the process will take three months," said Chipumha.

Chipumha said the new road design would cost US$520 000 of the total project cost estimated at US$400 million.

Although rehabilitation had already begun along smaller portions of Beatrice and Chivhu, dualisation is still pending.

"Due to political pressure, government has since begun on the 20-kilometre stretch from Beatrice and another 10 kilometres in Chivhu," said Chipumha.

Government will award nine local construction firms 50-kilometre portions of the highway.

Last year, Transport minister Joel Biggie Matiza said the government would float a US$250 million bond guaranteed by ZB Bank to fund the project, while negotiating with a new partner.

However, government is yet to float the bond, five months on in a move that is likely to further delay the dualisation project.
Matiza last month admitted that government was working on a shoe-string budget of US$150 million with only US$40 million having been disbursed for the rehabilitation of sections between Chivhu and Beatrice.

Matiza said the door was still open for foreign companies.

The Zimbabwe National Road Authority (Zinara) was expected to float infrastructure bonds to mobilise funds for upgrading the highway after government terminated a contract that had been awarded to Chinese contractor Afecc. But the process has stalled under unclear circumstances with sources saying government was avoiding debt.

Last year, Afecc's financiers expressed concern with the build, operate and transfer arrangement (BOT), which they deemed unfeasible. Government, on its part, failed to convince the company on how it would realise the full benefits of the investment.

Afecc had only committed to do the 133km stretch from Harare to Chivhu under the BOT plan, resulting in government looking for funds to start the project, while negotiations continue.

According to the 2019 Ministry of Finance Infrastructure Investment Plan, US$300 million will be disbursed to the project, comprising of US$50 million in fiscal resources and US$250 million proceeds raised through a Zinara infrastructure bond.

The ministry said the position was taken after government failed to upgrade the road network through the public-private partnership (PPPs) agreement due to funding and contractual disagreements with foreign companies.

The roadworks consist of phased dualisation, rehabilitation, and widening of the existing road from the current seven metres to the Southern Africa Transport and Communications Commission standard width of 12,5 metres.

Government hopes dualisation will help address ease traffic congestion around major cities and towns along the Harare-Beitbridge highway.

Dualisation of at least 10km towards major cities will be undertaken by local contractors, with Matiza saying government would prioritise local contractors while negotiating another deal with Afecc.

To augment the bond, the Japanese government will disburse US$6,3 million to upgrade the Makuti-Hellsgate section of the Harare-Chirundu highway.

The Harare-Beitbridge highway is part of the North-South Corridor linking the south-eastern port of Durban in South Africa to other Sadc and Comesa member states to the north, facilitating trade with the region and Africa. The increase in traffic volumes, coupled with the poor state of the road, has resulted in congestion, increased accidents and loss of lives and property.

- the idnependent

 0

You May Like These Videos

Comments

There are no comments.

Latest stories

Mugabe Aeroplanes sold for $12.5 million

by Mandla Ndlovu | 20 March 2019 | 183 Views

Chamisa opens up on his visit to Manicaland

by Mandla Ndlovu | 20 March 2019 | 178 Views

NetOne outpaces competitors, active subscriber base balloons

by Ndou Paul | 20 March 2019 | 123 Views

South Africa send support to Cyclone Idai-hit Manicaland

by ZimLive | 20 March 2019 | 125 Views

How to choose the right powder welding machine

by Tech Reporter | 20 March 2019 | 83 Views

No one will die of hunger, Mnangagwa tells cyclone victims

by Staff reporter | 20 March 2019 | 100 Views

Mnangagwa off to affected areas

by Staff reporter | 20 March 2019 | 87 Views

Mohadi opens tobacco selling season

by Staff reporter | 20 March 2019 | 98 Views

This is not it Mr Mnangagwa!

by Editorial - Daily News | 20 March 2019 | 129 Views

Obert Mpofu to appear before Bulawayo court

by Staff reporter | 20 March 2019 | 100 Views

Mnangagwa, Chamisa cannot lead dialogue

by Staff reporter | 20 March 2019 | 93 Views

Uproar over illiterate councillor

by Staff reporter | 20 March 2019 | 89 Views

Kwekwe VID receiving bribes in exchange for drivers' licences

by Staff reporter | 20 March 2019 | 92 Views

Lupane school forced to close over goblins

by Staff reporter | 20 March 2019 | 86 Views

Mnangagwa plans to stop using army in demos

by Staff reporter | 20 March 2019 | 111 Views

Government sells NetOne and TelOne

by Mandla Ndlovu | 20 March 2019 | 146 Views

How Prophet Isaiah Sovi foretold Cyclone Idai

by Mandla Ndlovu | 20 March 2019 | 179 Views

'Joshua Nkomo made Mugabe the leader of ZANU in 1975'

by Mandla Ndlovu | 20 March 2019 | 149 Views

Water shortage to increase in Harare

by Mandla Ndlovu | 20 March 2019 | 115 Views

#Cyclone Idai: Mnangagwa on the ground

by Staff reporter | 20 March 2019 | 112 Views

Zesa gets new board

by Staff reporter | 20 March 2019 | 100 Views

Chamisa wants MPs to push for Department of Civil Protection reform

by Staff reporter | 20 March 2019 | 109 Views

Heavyweights vie for ZACC posts

by Staff reporter | 20 March 2019 | 87 Views

Leyland eyes Zimbabwe bus plant

by Staff reporter | 20 March 2019 | 109 Views

Potraz summons Liquid over tariff hike

by Staff reporter | 20 March 2019 | 89 Views

ZCTU bosses' freedom bid quashed

by Staff reporter | 20 March 2019 | 53 Views

Over 100 trucks transporting Zimbabwe wheat stuck in Mozambique

by Staff reporter | 20 March 2019 | 91 Views

Ex-Zanu-PF Senator sued over $368k power debt

by Staff reporter | 20 March 2019 | 105 Views

Bulilima West MP bemoans absence of referral hospital

by Staff reporter | 20 March 2019 | 91 Views

MP takes council to task over floods

by Staff reporter | 20 March 2019 | 83 Views

Men jailed 2 years for defacing Mnangagwa banner

by Staff reporter | 20 March 2019 | 91 Views

Man (21) kills brother (15) over food

by Staff reporter | 20 March 2019 | 93 Views

Headman leaves behind 35 children

by Staff reporter | 20 March 2019 | 103 Views

Mash Central MDC youth leader out on bail

by Staff reporter | 20 March 2019 | 49 Views